You’ve probably noticed a lot of park upgrades over the past few years. It’s not all a coincidence. Almost exactly three years ago, the Village Board adopted a Comprehensive Outdoor Recreation Plan (CORP), and since then the board, along with the Department of Public Works, has acted on a number of the ideas laid out in that document. Here’s a look at what’s already been tackled, and what may be coming next.
What is the CORP, anyway?
The Village Board adopted the CORP in August 2023. It was intended to be a five-year roadmap, covering 2024 through 2028, developed by Village staff with their consultant (GRAEF), built on an inventory of all ten of the parks within the Village boundaries, a resident survey, and a comparison against peer North Shore communities. The plan also matters for the Village’s bottom line: having an adopted CORP is a prerequisite for applying for outdoor recreation grants through the Wisconsin DNR.
The community survey behind the plan drew 400 responses. Eighty-four percent of respondents said they were at least “somewhat satisfied” with the quality of Whitefish Bay’s parks, but when asked what needed work, three themes came up again and again: aging playground equipment, better accessibility, and continued restoration of the lakeshore, beaches and bluffs. Looking at what’s gotten built since, the Village has been checking those boxes.
What’s already happened

Klode Park bluff stabilization and stormwater management. The Village Board awarded the construction contract in June 2024. The design added a regenerative stormwater conveyance system, two bioswales, and native restoration and invasive-species removal across the bluff’s terraces, treating an estimated 75,000 gallons of stormwater runoff. Three grant sources totaling $250,000 funded it: the Fund for Lake Michigan, the Wisconsin Coastal Management Program, and MMSD Green Solutions. Construction was completed in 2025.

Klode Park landscaping. Reforestation and landscaping work, funded through an MMSD grant that also supported the arboretum at Library Park, wrapped up in October 2025.

Klode Park playground. After residents voted on concept designs, work began in April 2024 on a new playground to replace the decades old wooden structure. The Kid Builder Little Tikes structure was built while keeping the sandbox and tree/bush thicket intact.

Cahill Square Park playground. Residents also had the chance to vote on concept designs. Construction started in April 2025, and the new playground opened that summer. It replaced the old structure with a modular BCI Burke “Play That Moves You” structure, added poured-in-place and engineered wood fiber surfacing for better accessibility, and kept legacy features like the sandbox and swings.


Library Park Arboretum. The small green strip on Marlborough Drive just north of the library got a complete makeover. Work began in October 2025, with contractors clearing existing vegetation and invasive species before crews moved in to plant more than 150 new trees and shrubs representing over two dozen species. The Village’s Public Works staff followed up in spring 2026 with a new walking path through the grounds. The project was funded in part by a grant from the Milwaukee Metropolitan Sewerage District. The pathway officially opened July 24, 2026 — making it one of the freshest completed items on the whole list.
Beyond the headline projects, the Village has been working on less visible infrastructure projects as well. The most significant, of course, was a multi-million dollar repair of a 90-plus-year-old storm sewer that collapsed and opened a major sinkhole beneath Buckley and Big Bay Parks (a surprise project – not in the CORP). Stormwater management improvements have also been completed at Craig Counsell Park. On the smaller end, Cahill received a new accessible sidewalk connecting the playground to the warming house, bathrooms, and tennis courts.
What may come in the future
The CORP lays out a potential year-by-year Capital Improvement Plan through 2028, though every line item is subject to Village Board approval and funding as budgets are finalized. With the exception of the Klode Park warming house, the highlights below have not been formally adopted.
A few highlights:
- Klode Park warming house: the long-discussed replacement is in the design phase now, with initial concepts recently made public. It’s currently on the books for 2027 at roughly $1.5 million.
- A potential sand volleyball installation. Also penciled into the 2027 CIP, but hasn’t been formally presented to the Public Works Committee yet.
- Klode Park trail replacement and stairwell repair: for 2027.
- Cahill Park Pavilion Upgrade: for 2028.
Where to see it yourself
The full plan, including the park-by-park inventory, survey results, and year-by-year CIP budget, is available from the Village here.